As of March 1, EPS continues the rehabilitation of PSHPP Bajina Bašta

2/6/2025
The Trial Run of the first rehabilitated unit completed

The rehabilitated unit in the pumped-storage hydro power plant Bajina Bašta has successfully completed 30-days Trial Run, and as of March 1, Elektroprivreda Srbije will begin the modernization of the second unit. Upon completion of the rehabilitation of our only pumped-storage hydro power plant, which was built 43 years ago, the reliability of our power system will be significantly improved.

During the Trial Run under both, pumping and turbine modes, the first rehabilitated unit performed without a single outage, under the supervision of experts from the Japanese company Toshiba and local institutes Nikola Tesla and Mihajlo Pupin. All parameters of the unit operation were intensively monitored and it was confirmed that the set rehabilitation goals were achieved.

- The rehabilitation of PSHPP Bajina Bašta is one of the most important investments in Elektroprivreda Srbije because it will provide decades of reliability of operation and will provide a significant contribution to the energy security of Serbia - said Dušan Živković, General Manager of EPS.

PSHPP Bajina Bašta is the only pumped-storage hydro power plant within EPS and is an important reserve in the Serbian power system during periods of increased electricity consumption or during dry periods, as well as for all those times when there is a shortage of electricity.